On Top was selected to provide a total rewire and major design-and-construct reconfiguration of the 1950s Zammit Smallgoods facility at Pendle Hill with Wiley & Co.
Project overview
Scope delivered by On Top.
On Top was selected to provide a total rewire and major design-and-construct reconfiguration of the 1950s Zammit Smallgoods facility at Pendle Hill with Wiley & Co.
Electrical scope
- New 1,500 A pad-mounted-substation LV main switchboard
- New external power-factor-correction and active-harmonic-filtering unit
- Three new 630 A main distribution boards
- Seven new 250 A distribution boards
- New cable trays and submain cabling to the new boards
- New subcircuit cabling
- New HACCP lighting, power and stainless-steel conduits
Project outcome